* 1. After one year of construction, an office building is scheduled for completion on 30 January. The landscaping work needs to start 15 days prior to the building’s completion. Which of the following relationships most likely represents the relationship of the start of landscaping work to the completion of the office building?

Question Title

* 2. In a project, Activity A has a duration of four days and begins on the morning of Monday the fourth. The successor Activity, B, has a Finish-to-Start (FS) relationship with A. The Finish-to-Start relationship has two days of lag, and Activity B has a duration of three days. If Saturday and Sunday are non-working days, which of the following statements is true?

Question Title

* 3. Midway through a project, a project manager determined the project was running far behind schedule. If the project manager needs to shorten the project schedule without changing the project scope, which of the following schedule compression techniques could he use?

Question Title

* 4. George is managing a construction project and currently sequencing the project activities and defining their logical relationships. Two activities have both the SS and FF relationships. How should George schedule these activities?

Question Title

* 5. Your construction project has been delayed by a few months due to some weather conditions. Completing the project by the contractual deadline is critical in order not only to avoid heavy penalties but to maintain your reputation. If you want to compress the project schedule, what are two of the recommended alternatives to consider?