PC5:8 - Duties and powers of a lead consultant and contract administrator Question Title * 1. Which of the following is not true about the role of the Lead Designer? It should not be an assumed role You require a separate appointment to cover this role beyond that of the Architect It requires more work, so should be charged for appropiately It is typically taken on by the Project Architect Question Title * 2. Whose responsibility might be creating a Design Responsibility Matrix at the beginning of Stage 02 - Concept Design? Contract Administrator Lead Consultant Project Lead Architect Question Title * 3. Which two of the following is not true of the function of the Contract Administrator? Provide Agency to the Contract Represent the Client's Interests Provide a Decision Making-Function To settle any Disputes that arise Question Title * 4. Which of the following is not a role and responsibility of the Contract Administrator? Submitting Payment Requests on behalf of the Contractor Considering claims submitted by the Contractor and Client Inviting, interviewing and processing tenders Assembling all contract document for execution Question Title * 5. Which of the following is not a typical reason for issuing an Architect's Instruction? To vary works To exclude persons from the site To reemedy workmanship, goods and materials which are not in accordnace with the contract To request release payment to the Contractor Done